A recent decision of the Supreme Court of Queensland highlights the importance of developers exercising caution when relying on sunset date clauses in off the plan apartment contracts.
In JYP Jiang Pty Ltd v CAV Gasworks Pty Ltd [2025] QSC 134, the court found that the developer had wrongfully terminated a contract using a sunset clause and was liable to compensate the buyer to the tune of $6.1 million in damages.
Background
In 2017, JYP Jiang Pty Ltd (the plaintiff/buyer) entered into a contract to purchase two sub-penthouses in the “Luminare” development in Newstead, QLD from CAV Gasworks Pty Ltd (the defendant/developer) for $4.2 million.
The contract provided for settlement would occur 14 days after the developer gave notice that the survey plan for the development had registered and titles had issued. If a certificate of occupancy had not been issued by then, settlement was to be postponed to 3 business days after the developer gives notice of its issuance.
Clause 8.1 stated that the developer must give notice once it becomes aware that the title conditions have been satisfied. However, the clause went on to say that the developer did not have to give the notice until it was satisfied that it could comply with all of its contractual obligations before settlement.
Although titles were issued in November 2022, the apartments were still less than 50% complete, and no certificate of occupancy had issued, meaning the developer could not lawfully provide possession.
The contract also included a ‘sunset clause’ entitling either party to terminate “if the seller cannot give [notice of issue of title] within 5.5 years of the contract date” (making the sunset date 30 December 2022).
The developer did not give notice of issue of title issuance but instead terminated the contract in April 2023, relying on the sunset clause. The certificate of occupancy had still not issued at that date. The developer subsequently sold the apartments for $8.8 million.
The buyer sued and won, with the court awarding $6.1 million in damages, being the difference between the contract price and the assessed market value of the apartments at the $10.3 million at the time the contract should have settled.
Key legal findings
The decision was based on an interpretation of the sunset clause and the notice clause.
The court found that the word “cannot” in the sunset clause meant that the developer could only rely on the clause if it was impossible to give the notice (i.e, the title condition had not been satisfied).
To interpret the sunset clause as granting the developer “an untrammelled and extremely wide power … to end the contract and deprive the buyer of the benefit of their bargain” would, the court said, not make commercial sense.
This was the case even though, under the notice clause, the developer had the right to defer giving the notice. It was noted that even if the notice had been given, settlement would not have been due until the certificate of occupancy had issued as provided for in the settlement clause.
Key takeaways for property developers
Authored by:
Gary Ko, Partner
Oo Hyun Park, Graduate